CAP Site - Crane Erection (TC 2) - 17th June 2026

Posted: 10 June 2026

Description of the Works

The erection of the second tower crane for the CAP site will take place on Wednesday 17th June. The 120 tonne mobile crane will arrive at 7am and the escort vehicle will take it to the site. Several articulated lorries will travel from Holywell car park to the site during the day to erect the crane. All works should be completed by 6pm on Wednesday. Whilst the articulated lorries are driving through site there may be traffic delays along university road this will only be temporary and traffic should run normally most of the day.

Timescale

Wednesday  17th June 7-am to 6-pm

How can I get more information and help?

The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.

Name and Job Title: - David Bell project Manager

Mobile: - 07729080152

Email: - d.w.bell@lboro.ac.uk